Work Profile Report [54W1156]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 शा0सं0-।/111277/2023 (ई पत्रावली संख्या-49995), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 29.03.2023
TS Amount (lakhs) : 61.94 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.94
Resanction Cost :
61.94
Tentative Cost :
61.94
Exp. Upto Last Fy :
20.21
For CFY 2024-2025
Remaining :
41.73
Demand :
41.73
Allotment :
42.67
Exp in CFY :
42.67
Total Up to Date Exp :
62.88
Work completed
Sanction on : 1 year 7 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
06 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand