Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.68 | 3.68 | 1.700 | 1.98 | 1.980 | 0.000 |
54W1163 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शा0सं0-।/111499/2023 (ई पत्रावली संख्या-49305), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 31.03.2023
TS Amount (lakhs) : 182.68 Lacs
Financial Detail
Sanction Cost : 182.68 Lacs
Resanction Cost : 182.68 Lacs
Exp. Upto Last Fy : 78.77 Lacs
For CFY 2024-2025
Remaining : 103.91 Lacs
Demand : 103.91 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 78.77 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 48 %
Up to Date : 48 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
4 weeks 1 day from now
18 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.500 कि0मी0 लम्बाई में टाॅप कोट एवं 1.700 कि0मी0 लम्बाई में इंटरलाॅकिंग टाइल्स का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 06-Feb-2024
Physical Peramenters