Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.235 | 2.23 | 2.230 | 0 | 0.000 | 0.000 |
54W1166 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश- ई पत्रावली संख्या-50715 लोक निर्माण अनुभाग-2, देहरादून, दिनांक 31.03.2023
TS Amount (lakhs) : 96.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.35
Resanction Cost :
103.59
Tentative Cost :
103.59
Exp. Upto Last Fy : 88.99
For CFY 2024-2025
Remaining : 14.60
Demand : 4.23
Allotment : 0.00
Exp in CFY : 9.81
Total Up to Date Exp : 98.80
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
4 months 3 weeks ago
23 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का भुगतान शेष है। -- as on 05-Dec-2023