Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.9 | 1.9 | 1.900 | 0 | 0.000 | 0.000 |
54W1169 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश- ई पत्रावली संख्या-50715 लोक निर्माण अनुभाग-2, देहरादून, दिनांक 31.03.2023
TS Amount (lakhs) : 73.5 Lacs
Financial Detail
Sanction Cost : 73.50 Lacs
Resanction Cost : 79.01 Lacs
Exp. Upto Last Fy : 79.00 Lacs
For CFY 2024-2025
Remaining : 0.01 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 79.00 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
2 months 2 weeks ago
05 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Physical Peramenters