Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.11 | 3.11 | 0.110 | 3 | 3.000 | 0.000 |
54W1170 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शासनादेश सं0-।/119371/2023 (ई0 पत्रावली संख्या-50023), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 03.05.2023
TS Amount (lakhs) : 187.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
187.28
Resanction Cost :
187.28
Tentative Cost :
187.28
Exp. Upto Last Fy : 0.68
For CFY 2024-2025
Remaining : 186.60
Demand : 186.60
Allotment : 25.08
Exp in CFY : 25.08
Total Up to Date Exp : 25.76
Construction Started
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 40 %
Sanction on :
1 year 2 months ago
03 May 2023
Tentative Completion date:
6 months 1 week from now
26 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.20 कि0मी0 लम्बाई में इंटरलाॅकिंग टाइल्स का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 02-Jul-2024
Physical Peramenters