Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.3 | 4.3 | 0.000 | 4.3 | 4.300 | 0.000 |
54W1178 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या ।/144160/2023 (ई0 पत्रावली संख्या-54195), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 07.08.2023
TS Amount (lakhs) : 73.68 Lacs
Financial Detail
Sanction Cost : 73.68 Lacs
Resanction Cost : 73.68 Lacs
Exp. Upto Last Fy : 20.41 Lacs
For CFY 2024-2025
Remaining : 53.27 Lacs
Demand : 53.27 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
1 month 3 weeks ago
25 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 05-Dec-2023
Physical Peramenters