Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.32 | 3.32 | 0.200 | 3.12 | 3.120 | 0.000 |
54W1184 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शासनादेश सं0- ।/161271/2023 (ई0 पत्रावली संख्या-47588), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 12.10.2023
TS Amount (lakhs) : 172.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
172.82
Resanction Cost :
172.82
Tentative Cost :
172.82
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 172.71
Demand : 172.71
Allotment : 77.42
Exp in CFY : 77.41
Total Up to Date Exp : 77.52
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 65 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
5 days 18 hours from now
23 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इंटरकोट, टाॅप कोट का कार्य पूर्ण 2.00 कि0मी0 लम्बाई में इंटरलाॅकिग टाईल्स का कार्य पूर्ण। अन्य कार्य प्रगति पर है -- as on 02-Jul-2024
Physical Peramenters