Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.32 | 3.32 | 0.200 | 3.12 | 3.120 | 0.000 |
54W1184 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 शासनादेश सं0- ।/161271/2023 (ई0 पत्रावली संख्या-47588), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 12.10.2023
TS Amount (lakhs) : 172.82 Lacs
Financial Detail
Sanction Cost : 172.82 Lacs
Resanction Cost : 172.82 Lacs
Exp. Upto Last Fy : 0.11 Lacs
For CFY 2024-2025
Remaining : 172.71 Lacs
Demand : 172.71 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.11 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
7 months 1 week ago
12 Oct 2023
Tentative Completion date:
2 months 3 days from now
23 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.20 कि0मी0 लम्बाई में इंटरकोट, टाॅप कोट एवं इंटरलाॅकि टाईल्स का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 08-Apr-2024
Physical Peramenters