Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.37 | 2.37 | 2.000 | 0.37 | 0.370 | 0.000 |
54W1211 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/167907/2023 (पत्रावली संख्या 50175), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 08.11.2023
TS Amount (lakhs) : 142.9 Lacs
Financial Detail
Sanction Cost : 142.90 Lacs
Resanction Cost : 142.90 Lacs
Exp. Upto Last Fy : 114.57 Lacs
For CFY 2024-2025
Remaining : 28.33 Lacs
Demand : 28.33 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 114.57 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
6 months 1 week ago
08 Nov 2023
Tentative Completion date:
2 months 3 days from now
23 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इंटर कोट, टाॅप कोट का कार्य पूर्ण। 2.50 कि0मी0 लम्बाई में इंटरलाॅकिंग टाइल्स का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 08-Apr-2024
Physical Peramenters