Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 1.500 | 0.7 | 0.700 | 0.000 |
54W1212 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/167907/2023 (पत्रावली संख्या 50175), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 08.11.2023
TS Amount (lakhs) : 112.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
112.73
Resanction Cost :
112.73
Tentative Cost :
112.73
Exp. Upto Last Fy : 74.51
For CFY 2024-2025
Remaining : 38.22
Demand : 38.22
Allotment : 9.63
Exp in CFY : 9.62
Total Up to Date Exp : 84.13
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 90 %
Sanction on :
8 months 1 week ago
08 Nov 2023
Tentative Completion date:
5 days 19 hours from now
23 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.10 कि0मी0 लम्बाई में इंटर कोट, टाॅप कोट एवं इंटरलाॅकिंग टाइल्स का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 04-Jun-2024