Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 1.000 | 4 | 4.000 | 0.000 |
54W1213 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/167907/2023 (पत्रावली संख्या 50175), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 08.11.2023
TS Amount (lakhs) : 286.21 Lacs
Financial Detail
Sanction Cost : 286.21 Lacs
Resanction Cost : 286.21 Lacs
Exp. Upto Last Fy : 0.14 Lacs
For CFY 2024-2025
Remaining : 286.07 Lacs
Demand : 286.07 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.14 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 months 1 week ago
08 Nov 2023
Tentative Completion date:
2 months 3 days from now
23 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 कि0मी0 लम्बाई में इंटर कोट, टाॅप कोट एवं इंटरलाॅकिंग टाइल्स का कार्य पूर्ण। अन्य कार्य प्रगति पर है। -- as on 08-Mar-2024
Physical Peramenters