Work Profile Report [54W1227]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई0 पत्रांक ।/199770/2024 (पत्रावली संख्या 56976), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 16.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
85.85
Resanction Cost :
85.85
Tentative Cost :
85.85
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
85.85
Demand :
85.85
Allotment :
54.67
Exp in CFY :
54.67
Total Up to Date Exp :
54.67
Work completed
Sanction on : 9 months 1 week ago
16 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
28 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 05-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: