Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.82 | 1.82 | 0.000 | 1.82 | 1.820 | 0.000 |
54W1227 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/199770/2024 (पत्रावली संख्या 56976), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 16.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.85
Resanction Cost :
85.85
Tentative Cost :
85.85
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 85.85
Demand : 85.85
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
4 months 1 day ago
16 Mar 2024
Tentative Completion date:
8 months 2 days from now
20 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दिनांक 10.07.2024 को निविदा खोली जानी है। -- as on 02-Jul-2024
Physical Peramenters