Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 |
54W1231 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई0 पत्रांक ।/176723/2023 (पत्रावली संख्या 50715), लोक निर्माण अनुभाग-2, देहरादून, दिनांक 20-12-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2.86
Resanction Cost :
2.86
Tentative Cost :
2.86
Exp. Upto Last Fy : 0.30
For CFY 2024-2025
Remaining : 2.56
Demand : 2.56
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.30
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
6 months 3 weeks ago
20 Dec 2023
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 26-Jun-2024
Physical Peramenters