Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.7 | 1.7 | 1.7 | 0 |
54W682 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 62(1)/।।।(2)/16-15(मु0मं0घो0) /2015, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 12.01.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
217.94
Resanction Cost :
578.67
Tentative Cost :
578.67
Exp. Upto Last Fy : 0.20
For CFY 2024-2025
Remaining : 578.47
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
8 years 6 months ago
12 Jan 2016
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रस्तावित मार्ग में मोथरोवाला एवं भारूवाला ग्रामसभा के प्रभावित कास्तकारों द्वारा ग्राम सभा मोथरोवाला के कास्तकारों ने आपसी समझौते द्वारा अपनी जमीन देने हेतु निशुल्क एन0ओ0सी0 प्रदान कर दी गयी है तथा ग्रामसभा भारूवाला के निवासियों द्वारा निशुल्क भूमि उपलब्ध कराये जाने हेतु विचार विमर्श किया जा रहा है। वर्तमान में संयोजकता कच्चे मार्ग के रूप में उपलब्ध करा दी गयी है एवं द्वितीय रचाण का आगणन गठन की कार्यवाही अंतिम चरण में है। -- as on 08-Apr-2024
Physical Peramenters