Work Profile Report [54W684]

जनपद देहरादून में बल्लीवाला चैक पर लेफ्ट टर्न फ्री करने हेतु भू-अध्याप्ति कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 8204/।।।(2)/15-45(प्रा0आ0)/2016, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 02.02.2016

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

185.00

Resanction Cost :

185.00

Tentative Cost :

185.00

Exp. Upto Last Fy :

91.76

For CFY 2025-2026

Remaining :

93.24

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

91.76

Construction Started

Sanction on : 9 years 5 months ago

02 Feb 2016

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

1 %

Tentative Completion date on : 8 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

परिसम्पत्तियों का मुआवजा आपसी समझौते द्वारा भुगतान किया जा चुका है। अवशेष परिसम्पत्तियों के भूमि अधिग्रहण प्रस्ताव विशेष भूमि अध्याप्ति अधिकारी, देहरादून को प्रेषित। -- as on 31-Jul-2020

Rating : 59

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: