Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
54W724 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2468/।।।(2)/16-16(एम0एल0ए0)/ 2015, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 16.09.2016
TS Amount (lakhs) : 240.86 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
240.86
Resanction Cost :
240.86
Tentative Cost :
240.86
Exp. Upto Last Fy : 104.23
For CFY 2024-2025
Remaining : 136.63
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 104.23
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 10 months ago
16 Sep 2016
Tentative Completion date:
4 months 2 days ago
15 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-Apr-2024
Physical Peramenters