Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
54W736 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4657(1)/।।।-2(मा0मु0घो0)/2013, दिनांक 30.08.2013
TS Amount (lakhs) : 42.12 Lacs
Financial Detail
Sanction Cost : 42.12 Lacs
Resanction Cost : 42.12 Lacs
Exp. Upto Last Fy : 5.54 Lacs
For CFY 2024-2025
Remaining : 36.58 Lacs
Demand : 36.58 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5.54 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 1 %
Sanction on :
10 years 8 months ago
30 Aug 2013
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
इस कार्यालय के पत्रांक 1786/25 सी0, दिनांक 02.05.2024 द्वारा सी0ए0 लैण्ड उपलब्ध कराने हेतु जिलाधिकारी, देहरादून से अनुरोध किया गया है। -- as on 03-May-2024
Physical Peramenters