Work Profile Report [54W874]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 1639/।।।(2)/18-16(एम0एल0ए0) /2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 24.04.2018
TS Amount (lakhs) : 212.23 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
212.23
Resanction Cost :
228.14
Tentative Cost :
228.14
Exp. Upto Last Fy :
217.49
For CFY 2024-2025
Remaining :
10.65
Demand :
5.00
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
217.49
In Maintenance After Completion
Sanction on : 6 years 8 months ago
24 Apr 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 4 weeks ago
25 Nov 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand