Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.500 | 0 | 0.000 | 0.000 |
54W874 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0- 1639/।।।(2)/18-16(एम0एल0ए0) /2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 24.04.2018
TS Amount (lakhs) : 212.23 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
212.23
Resanction Cost :
228.14
Tentative Cost :
228.14
Exp. Upto Last Fy : 217.49
For CFY 2024-2025
Remaining : 10.65
Demand : 5.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 217.49
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 2 months ago
24 Apr 2018
Tentative Completion date:
3 years 7 months ago
25 Nov 2020
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Physical Peramenters