Work Profile Report [54W933]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-1319/।।।(2)/19-16(एम0एल0ए0) /2017 टी0सी0, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 08.03.2019
TS Amount (lakhs) : 258.63 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
258.63
Resanction Cost :
277.53
Tentative Cost :
277.53
Exp. Upto Last Fy :
266.10
For CFY 2024-2025
Remaining :
11.43
Demand :
6.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
266.10
In Maintenance After Completion
Sanction on : 5 years 9 months ago
08 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 2 months ago
30 Sep 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। कार्य अनुरक्षण के अन्तर्गत है। -- as on 08-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand