Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.33 | 2.33 | 2.330 | 0 | 0.000 | 0.000 |
55W1499 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1637/।।।(2)/20-35(एम.एल.ए.) /2017 टी0सी0 दिनांक 04.09.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
125.79
Resanction Cost :
125.79
Tentative Cost :
125.79
Exp. Upto Last Fy : 122.10
For CFY 2024-2025
Remaining : 3.69
Demand : 0.63
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 122.10
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 10 months ago
04 Sep 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण । अनुरक्षण का कार्य कराया जायेगा, जिस हेतु धनावंटन की मांग की गयी है। -- as on 15-Apr-2024