Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.92 | 1.92 | 0.000 | 1.92 | 1.920 | 0.000 |
55W1595 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2323/III(2)/21-35(M.L.A.)/2017 T.C.
TS Amount (lakhs) : 61.44 Lacs
Financial Detail
Sanction Cost : 61.44 Lacs
Resanction Cost : 61.44 Lacs
Exp. Upto Last Fy : 18.08 Lacs
For CFY 2024-2025
Remaining : 43.36 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 18.08 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
2 years 9 months ago
27 Jul 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग, इंटरकोट तक कार्य पूर्ण व 1.72 कि0मी0 में टाॅपकोट का कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 29-Apr-2024
Physical Peramenters