Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.92 | 1.92 | 0.000 | 1.92 | 1.920 | 1.920 |
55W1595 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2323/III(2)/21-35(M.L.A.)/2017 T.C.
TS Amount (lakhs) : 61.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.44
Resanction Cost :
61.44
Tentative Cost :
61.44
Exp. Upto Last Fy : 18.08
For CFY 2024-2025
Remaining : 43.36
Demand : 25.00
Allotment : 2.18
Exp in CFY : 2.18
Total Up to Date Exp : 20.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
27 Jul 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 05/2024 -- as on 28-May-2024
Physical Peramenters