Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.68 | 0.68 | 0.680 | 0 | 0.000 | 0.000 |
55W1625 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3608/III(2)/21-26(M.L.A.)/2017 T.C.-I
TS Amount (lakhs) : 54.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.32
Resanction Cost :
54.32
Tentative Cost :
54.32
Exp. Upto Last Fy : 40.54
For CFY 2024-2025
Remaining : 13.78
Demand : 10.00
Allotment : 10.00
Exp in CFY : 10.00
Total Up to Date Exp : 50.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
14 Sep 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters