Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.500 | 0 | 0.000 | 0.000 |
55W1648 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4833/III(2)/21-27(M.L.A.)/2017 T.C. II
TS Amount (lakhs) : 462.51 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
462.51
Resanction Cost :
462.51
Tentative Cost :
462.51
Exp. Upto Last Fy : 448.78
For CFY 2024-2025
Remaining : 13.73
Demand : 2.31
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 448.78
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
12 Oct 2021
Tentative Completion date:
1 year 6 months ago
06 Jan 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण। अनुरक्षण का कार्य कराया जायेगा, जिस हेतु धनावंटन की मांग की गयी है। -- as on 15-Apr-2024
Physical Peramenters