Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.22 | 3.22 | 3.220 | 0 | 0.000 | 0.000 |
55W1673 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5631/III(2)/21-26(M.L.A.)/2017 T.C.
TS Amount (lakhs) : 41.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.15
Resanction Cost :
41.15
Tentative Cost :
41.15
Exp. Upto Last Fy : 32.00
For CFY 2024-2025
Remaining : 9.15
Demand : 7.00
Allotment : 2.47
Exp in CFY : 2.47
Total Up to Date Exp : 34.47
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
17 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters