Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.91 | 0.91 | 0.910 | 0 | 0.000 | 0.000 |
55W1694 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5692/III(2)/21-35(M.L.A.)/2017
TS Amount (lakhs) : 77.04 Lacs
Financial Detail
Sanction Cost : 77.04 Lacs
Resanction Cost : 77.04 Lacs
Exp. Upto Last Fy : 52.88 Lacs
For CFY 2024-2025
Remaining : 24.16 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 52.88 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 5 months ago
24 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters