Work Profile Report [55W1711]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6011/III(2)/21-25(M.L.A.)/2017 T.C.-II
TS Amount (lakhs) : 85.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
85.88
Resanction Cost :
85.88
Tentative Cost :
10.00
Saving
75.88
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
85.88
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 2 years 11 months ago
11 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
30 %
Tentative Completion date on : 4 months 6 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.50 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में विवाद है। -- as on 30-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand