Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
55W1716 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6022/III(2)/21-27(M.L.A.)/2017 T.C.-II
TS Amount (lakhs) : 510.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
510.91
Resanction Cost :
510.91
Tentative Cost :
510.91
Exp. Upto Last Fy : 473.74
For CFY 2024-2025
Remaining : 37.17
Demand : 4.64
Allotment : 14.00
Exp in CFY : 2.46
Total Up to Date Exp : 476.20
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
14 Dec 2021
Tentative Completion date:
1 year 2 months ago
12 May 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण । अनुरक्षण का कार्य कराया जायेगा, जिस हेतु धनावंटन की मांग की गयी है। -- as on 15-Apr-2024
Physical Peramenters