Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.9 | 0.9 | 0.000 | 0.9 | 0.900 | 0.900 |
55W1727 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6106/III(2)/21-35(M.L.A.)/2017 T.C.
TS Amount (lakhs) : 39.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.90
Resanction Cost :
39.90
Tentative Cost :
39.90
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 39.90
Demand : 25.00
Allotment : 10.61
Exp in CFY : 10.61
Total Up to Date Exp : 10.61
Work completed
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
16 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 05/2024 -- as on 30-May-2024
Physical Peramenters