Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.87 | 0.87 | 0.870 | 0 | 0.000 | 0.000 |
55W1803 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1/111700/2023 लोक निर्माण अनुभाग-2 देहरादून
TS Amount (lakhs) : 29.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.31
Resanction Cost :
29.31
Tentative Cost :
29.31
Exp. Upto Last Fy : 11.39
For CFY 2024-2025
Remaining : 17.92
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.39
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters