Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.800 | 0 | 0.000 | 0.000 |
55W1813 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1/111991/2023 लोक निर्माण अनुभाग-2 देहरादून
TS Amount (lakhs) : 55.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.47
Resanction Cost :
55.47
Tentative Cost :
55.47
Exp. Upto Last Fy : 35.58
For CFY 2024-2025
Remaining : 19.89
Demand : 10.00
Allotment : 1.38
Exp in CFY : 1.38
Total Up to Date Exp : 36.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters