Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.82 | 1.82 | 0.250 | 1.57 | 1.570 | 0.000 |
55W1820 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1/122461/2023 लोक निर्माण अनुभाग-2 देहरादून
TS Amount (lakhs) : 74.26 Lacs
Financial Detail
Sanction Cost : 74.26 Lacs
Resanction Cost : 74.26 Lacs
Exp. Upto Last Fy : 33.20 Lacs
For CFY 2024-2025
Remaining : 41.06 Lacs
Demand : 15.00 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 33.20 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 2 hours ago
19 May 2023
Tentative Completion date:
2 months 1 week from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाॅप कोट तक कार्य पूर्ण, 0.25 कि0मी0 में मार्ग कार्य पूर्ण, शेष कार्य प्रगति में है।
(उक्त कार्य पर माह 01/2024 तक राज्य योजना मद से रु0 12.08 लाख का व्यय किया गया है)
-- as on 01-Feb-2024
Physical Peramenters