Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 1.600 | 0 | 0.000 | 0.000 |
55W1821 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1/122461/2023 लोक निर्माण अनुभाग-2 देहरादून
TS Amount (lakhs) : 61.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.73
Resanction Cost :
61.73
Tentative Cost :
61.73
Exp. Upto Last Fy : 40.98
For CFY 2024-2025
Remaining : 20.75
Demand : 5.00
Allotment : 5.00
Exp in CFY : 2.48
Total Up to Date Exp : 43.46
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
6 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण अनुरक्षण कार्य किया जाना है।
(उक्त कार्य पर माह 01/2024 तक राज्य योजना मद से रु0 36.46 लाख का व्यय किया गया है)
-- as on 01-Jul-2024
Physical Peramenters