Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 1.000 | 0.6 | 0.600 | 0.600 |
55W1822 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1/122461/2023 लोक निर्माण अनुभाग-2 देहरादून
TS Amount (lakhs) : 59.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.35
Resanction Cost :
59.35
Tentative Cost :
59.35
Exp. Upto Last Fy : 32.59
For CFY 2024-2025
Remaining : 26.76
Demand : 15.00
Allotment : 15.00
Exp in CFY : 18.49
Total Up to Date Exp : 51.08
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024
(उक्त कार्य पर माह 01/2024 तक राज्य योजना मद से रु0 10.20 लाख का व्यय किया गया है)
-- as on 29-Jun-2024
Physical Peramenters