Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.05 | 1.05 | 0.000 | 1.05 | 1.050 | 0.000 |
55W1823 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 136151/2023/PWD2-BUD/ANBU/33/2023-III-2-Public Works Department
TS Amount (lakhs) : 26.63 Lacs
Financial Detail
Sanction Cost : 26.63 Lacs
Resanction Cost : 26.63 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 26.63 Lacs
Demand : 25.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
10 months 1 week ago
10 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 07-Nov-2023
Physical Peramenters