Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.55 | 3.55 | 3.550 | 0 | 0.000 | 0.000 |
55W1828 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/139598/2023/PWD2-BUD-ANBU/25/2023-III-2-Public Works Department
TS Amount (lakhs) : 80.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
80.45
Resanction Cost :
80.45
Tentative Cost :
80.45
Exp. Upto Last Fy : 52.91
For CFY 2024-2025
Remaining : 27.54
Demand : 27.50
Allotment : 27.33
Exp in CFY : 27.33
Total Up to Date Exp : 80.24
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 3 weeks ago
21 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters