Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.600 | 0.7 | 0.700 | 0.000 |
55W1837 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 72.12 Lacs
Resanction Cost : 72.12 Lacs
Exp. Upto Last Fy : 29.39 Lacs
For CFY 2024-2025
Remaining : 42.73 Lacs
Demand : 10.00 Lacs
Allotment : 4.54 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 29.39 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
9 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाॅपकोट तक कार्य पूर्ण, 0.60 कि0मी0 में मार्ग कार्य पूर्ण, शेष कार्य प्रगति में है।
(उक्त कार्य पर माह 01/2024 तक राज्य योजना मद से रु0 0.09 लाख का व्यय किया गया है)
-- as on 29-Apr-2024
Physical Peramenters