Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 2.000 |
55W1838 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.95
Resanction Cost :
93.95
Tentative Cost :
93.95
Exp. Upto Last Fy : 53.16
For CFY 2024-2025
Remaining : 40.79
Demand : 30.00
Allotment : 30.00
Exp in CFY : 16.17
Total Up to Date Exp : 69.33
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 95 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग कार्य पूर्ण, पटरी आदि कार्य प्रगति में है।
(उक्त कार्य पर माह 01/2024 तक राज्य योजना मद से रु0 0.49 लाख का व्यय किया गया है)
-- as on 29-Jun-2024
Physical Peramenters