Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.68 | 1.68 | 1.000 | 0.68 | 0.680 | 0.680 |
55W1839 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 89.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.76
Resanction Cost :
97.76
Tentative Cost :
97.76
Exp. Upto Last Fy : 57.29
For CFY 2024-2025
Remaining : 40.47
Demand : 30.00
Allotment : 0.11
Exp in CFY : 0.11
Total Up to Date Exp : 57.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
1 month 2 days ago
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 05/2024 -- as on 31-May-2024
Physical Peramenters