Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.600 | 0.4 | 0.400 | 0.000 |
55W1841 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 59.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.73
Resanction Cost :
59.73
Tentative Cost :
59.73
Exp. Upto Last Fy : 14.29
For CFY 2024-2025
Remaining : 45.44
Demand : 20.00
Allotment : 5.00
Exp in CFY : 3.16
Total Up to Date Exp : 17.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.60 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में ग्रामीणों द्वारा विवाद किया जा रहा है। विवाद के निस्तारण के बाद ही कार्य पूर्ण किया जाना संभव होगा। -- as on 01-Jul-2024
Physical Peramenters