Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.600 | 0.4 | 0.400 | 0.000 |
55W1841 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 59.73 Lacs
Financial Detail
Sanction Cost : 59.73 Lacs
Resanction Cost : 59.73 Lacs
Exp. Upto Last Fy : 14.29 Lacs
For CFY 2024-2025
Remaining : 45.44 Lacs
Demand : 20.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 14.29 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
9 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.60 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-Mar-2024
Physical Peramenters