Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.75 | 1.75 | 1.750 | 0 | 0.000 | 0.000 |
55W1842 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/142766/2023/PWD2-BUD-ANBU/36/2023-III-2-Public Works Department
TS Amount (lakhs) : 89.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.85
Resanction Cost :
89.85
Tentative Cost :
89.85
Exp. Upto Last Fy : 66.15
For CFY 2024-2025
Remaining : 23.70
Demand : 20.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 66.15
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण दायित्व शेष। -- as on 13-Apr-2024
Physical Peramenters