Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.53 | 0.53 | 0.200 | 0.33 | 0.330 | 0.330 |
55W1872 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 37.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.32
Resanction Cost :
37.32
Tentative Cost :
37.32
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 37.22
Demand : 25.00
Allotment : 30.94
Exp in CFY : 30.94
Total Up to Date Exp : 31.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
9 months 4 hours ago
17 Oct 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2024 -- as on 29-Jun-2024
Physical Peramenters