Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.53 | 0.53 | 0.200 | 0.33 | 0.330 | 0.000 |
55W1872 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 37.32 Lacs
Financial Detail
Sanction Cost : 37.32 Lacs
Resanction Cost : 37.32 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 37.22 Lacs
Demand : 25.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
7 months 2 days ago
17 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.20 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-Mar-2024
Physical Peramenters