Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.36 | 1.36 | 0.000 | 1.36 | 1.360 | 1.200 |
55W1874 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 36.16 Lacs
Financial Detail
Sanction Cost : 36.16 Lacs
Resanction Cost : 36.16 Lacs
Exp. Upto Last Fy : 0.71 Lacs
For CFY 2024-2025
Remaining : 35.45 Lacs
Demand : 30.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 88 %
Up to Date : 88 %
Sanction on :
7 months 1 day ago
17 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.20 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 29-Apr-2024
Physical Peramenters