Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.54 | 0.54 | 0.000 | 0.54 | 0.000 | 0.000 |
55W1875 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 17.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.45
Resanction Cost :
17.45
Tentative Cost :
17.45
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 17.35
Demand : 2.00
Allotment : 2.65
Exp in CFY : 2.65
Total Up to Date Exp : 2.75
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 months 5 hours ago
17 Oct 2023
Tentative Completion date:
8 months 1 week from now
25 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
सीवर लाईन का कार्य किया जा रहा है, सीवर कार्य पूर्ण किये जाने के पश्चात ही स्वीकृत कार्य प्रारम्भ किया जा सकेगा। -- as on 01-Jul-2024
Physical Peramenters