Work Profile Report [55W1877]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 22.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
22.90
Resanction Cost :
22.90
Tentative Cost :
15.11
Saving
7.79
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
22.79
Demand :
10.00
Allotment :
8.66
Exp in CFY :
8.66
Total Up to Date Exp :
8.77
Construction Started
Sanction on : 1 year 1 month ago
17 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
45 %
Tentative Completion date on : 3 months 1 week ago
15 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.50 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में विवाद होने के कारण कार्य नहीं हो सका है। -- as on 31-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: