Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.02 | 1.02 | 0.000 | 1.02 | 0.000 | 0.500 |
55W1877 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 22.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
22.90
Resanction Cost :
22.90
Tentative Cost :
22.90
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 22.79
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.11
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 45 %
Sanction on :
9 months 5 hours ago
17 Oct 2023
Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.50 कि0मी0 में कार्य पूर्ण,शेष कार्य प्रगति में है। -- as on 29-Jun-2024
Physical Peramenters