Administrative Approval Detail : 1/162536/2023/PWD2-BUD-ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.29
Resanction Cost :
53.29
Tentative Cost :
53.29
Exp. Upto Last Fy :
0.20
For CFY 2024-2025
Remaining :
53.09
Demand :
51.23
Allotment :
47.23
Exp in CFY :
47.23
Total Up to Date Exp :
47.43
Work completed
Sanction on : 1 year 1 month ago
17 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 1 week ago
15 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यपूर्ण 04/2024 -- as on 29-Apr-2024