Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.55 | 0.55 | 0.000 | 0.55 | 0.550 | 0.050 |
55W1890 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O.No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 41.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.03
Resanction Cost :
41.03
Tentative Cost :
41.03
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 40.93
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 5 %
Sanction on :
7 months 5 days ago
12 Dec 2023
Tentative Completion date:
1 month 4 weeks from now
15 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.050 कि0मी0 में कार्य पूर्ण,शेष कार्य प्रगति में है। -- as on 29-Jun-2024
Physical Peramenters