Work Profile Report [55W1891]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 32.5 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.50
Resanction Cost :
32.50
Tentative Cost :
28.68
Saving
3.82
Exp. Upto Last Fy :
3.68
For CFY 2024-2025
Remaining :
28.82
Demand :
10.84
Allotment :
7.89
Exp in CFY :
7.89
Total Up to Date Exp :
11.57
Construction Started
Sanction on : 11 months 1 week ago
12 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
75 %
Tentative Completion date on : 3 months 3 weeks from now
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.60 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में अशोक विहार में सीवर लाईन का कार्य किया जाना है, उसके उपरान्त ही शेष कार्य पूर्ण किया जायेगा। -- as on 30-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: