Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.200 | 0.3 | 0.300 | 0.200 |
55W1892 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 43.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.64
Resanction Cost :
43.64
Tentative Cost :
43.64
Exp. Upto Last Fy : 0.71
For CFY 2024-2025
Remaining : 42.93
Demand : 35.00
Allotment : 17.68
Exp in CFY : 17.68
Total Up to Date Exp : 18.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 80 %
Sanction on :
7 months 5 days ago
12 Dec 2023
Tentative Completion date:
1 month 2 days from now
20 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.40 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 28-May-2024
Physical Peramenters