Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.78 | 0.78 | 0.300 | 0.48 | 0.480 | 0.200 |
55W1893 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 33.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
33.91
Resanction Cost :
33.91
Tentative Cost :
33.91
Exp. Upto Last Fy : 0.11
For CFY 2024-2025
Remaining : 33.80
Demand : 25.00
Allotment : 8.37
Exp in CFY : 8.37
Total Up to Date Exp : 8.48
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
7 months 5 days ago
12 Dec 2023
Tentative Completion date:
6 months 4 weeks from now
15 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.50 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में स्थानीय जनता द्वारा सी0सी0 मार्ग की मांग की जा र ही है, जिस कारण शेष लम्बाइ में कार्य बाधित किया गया है। -- as on 01-Jul-2024
Physical Peramenters