Work Profile Report [55W1893]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. No. 1/174460/2023/PWD2-BUD/ANBU/28/2023-III-2-Public Works Department
TS Amount (lakhs) : 33.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
33.91
Resanction Cost :
33.91
Tentative Cost :
22.50
Saving
11.41
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
33.80
Demand :
22.00
Allotment :
18.42
Exp in CFY :
18.42
Total Up to Date Exp :
18.53
Construction Started
Sanction on : 1 year 1 week ago
12 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
75 %
Tentative Completion date on : 1 month 3 weeks from now
15 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.60 कि0मी0 में कार्य पूर्ण, शेष लम्बाई में स्थानीय जनता द्वारा टाईल्स के स्थान पर सी0सी0 की मांग की जा रही है। -- as on 07-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: