Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
55W1895 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1/175558/2023/पीडब्लूडी2-बीयूडी/ एएनबीयू/36/2023-।।।-2-लो0नि0वि0
TS Amount (lakhs) : 86.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
86.78
Resanction Cost :
86.78
Tentative Cost :
86.78
Exp. Upto Last Fy : 0.08
For CFY 2024-2025
Remaining : 86.70
Demand : 50.00
Allotment : 20.00
Exp in CFY : 12.08
Total Up to Date Exp : 12.16
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 50 %
Sanction on :
6 months 4 weeks ago
19 Dec 2023
Tentative Completion date:
1 month 4 weeks from now
15 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टाॅप कोट तक कार्य पूर्ण , 0.80 कि0मी0 में बी0एम0 कार्य कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 01-Jul-2024
Physical Peramenters