Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.91 | 0.91 | 0.000 | 0.91 | 0.000 | 0.000 |
55W1902 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O.No. 1/181020/2024 PWD2-BUD/ANBU/28/2023-III-2-Public Works Department-Part(1)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.39
Resanction Cost :
63.39
Tentative Cost :
63.39
Exp. Upto Last Fy : 0.07
For CFY 2024-2025
Remaining : 63.32
Demand : 5.00
Allotment : 0.25
Exp in CFY : 0.25
Total Up to Date Exp : 0.32
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
8 months 1 week from now
25 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
इस कार्य पर अभी भी सीवर का कार्य प्रगति में है, तथा सीवर पूर्ण किये जाने के पश्चात ही स्वीकृत कार्य प्रारम्भ किया जा सकेगा। -- as on 01-Jul-2024
Physical Peramenters